Deal #10571

Philippines
Created at
2024-08-29
Last update
2024-10-17
Last full update
2024-10-17

Land area

Intended size
25 ha
Size under contract (leased or purchased area)
  • [2016-03-12, current] 25 ha
Size in operation (production)
  • [2016-03-12, current] 25 ha
Comment on land area
Clark Air Base, a former United States military facility

Intention of investment

Intention of investment
  • [2016-03-12, current] Solar park (25 ha)
Comment on intention of investment
The solar park is found in the New Clark City (NCC), the Philippines’ first smart and green metropolis. NCC is a P607-billion metropolis touted as the country’s first “climate-change resilient” city. Read more: https://newsinfo.inquirer.net/1138945/p607-b-clark-green-city-to-displace-aeta-communities#ixzz8oucpzerY Follow us: @inquirerdotnet on Twitter | inquirerdotnet on Facebook

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2015-09] Startup phase (no production)
  • [2016-03-12, current] In operation (production)
Comment on implementation status
The 22.326 MWp solar plant within the Clark Freeport Zone, Pampanga, Luzon, began site-preparation and construction in September 2015. Project Clark has now been successfully constructed and commissioned, and has been operating since March 12, 2016

Contract farming

Contract farming
No