Land area
Intended size
25 521 ha
Size under contract (leased or purchased area)
- [current] 25 521 ha
Comment on land area
The wind farm spans 25,521.98 hectares
Intention of investment
Intention of investment
- [2011, current] Wind farm (25 521 ha)
Comment on intention of investment
The intention to develop the Brandvalley Wind Farm began on 2011, when G7 Renewable Energies started the project's development process.
Carbon offset project
Carbon offset project
No
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2023, current] Startup phase (no production)
Comment on implementation status
It is currently in the construction phase, with commercial operations expected to begin in late 2024.