2. Data source #-oW34KfU

Type
Company sources
Publication title
Resumo Público do Manejo Florestal
Date
2021-09
Name
Mahal Empreendimentos e Participações S.A. & Novo Oeste Gestão de Ativos Florestais S.A.
Organisation
Mahal Empreendimentos e Participações S.A. & Novo Oeste Gestão de Ativos Florestais S.A.
Comment on data source
The document provides information about the forest management of the companies Mahal Empreendimentos e Participações S.A. and Novo Oeste Gestão de Ativos Florestais S.A., and it includes details on the amount of land owned by these companies.

3. Data source #SUee3Zlq

Type
Government sources
Publication title
Polo Mundial de Celulose: governo entrega licença para instalação da fábrica da Arauco em MS
Date
2024-05-10
Name
Agência de Notícias do Governo do Estado de Mato Grosso do Sul
Organisation
Agência de Notícias do Governo do Estado de Mato Grosso do Sul
Comment on data source
The news reports on the issuance of the installation license by the state government.

6. Data source #XVQRMG59

Type
Company sources
Publication title
Relatório de Impacto Ambiental Unidade Inocência
Date
2023
Name
Pöyry Tecnologia Ltda.
Organisation
Pöyry Tecnologia Ltda.
Comment on data source
Environmental Impact Report (RIMA) submitted to the State Institute of Environmental Affairs of Mato Grosso do Sul (IMASUL) as a requirement for obtaining the installation license for the project.

7. Data source #UM_p_FT4

Type
Company sources
Publication title
Respostas às perguntas da sociedade civil
Date
2023
Name
Arauco
Organisation
Arauco
Comment on data source
The document addresses the inquiries submitted by the civil society through the State Institute of Environmental Affairs of Mato Grosso do Sul (IMASUL). This is a requirement in the environmental licensing process. The questions were answered by the company Arauco. The document reflects a dialogue with civil society; however, it does not constitute a free, prior, and informed consultation as provided by Convention 169 of the International Labour Organization. The document lacks a date, but it was published in 2023, considering that the Environmental Impact Report is dated 2023 and the construction of the factory began in 2024.

8. Data source #U3oC1K9F

Type
Media report
Publication title
Arauco apresenta detalhes da instalação da fábrica de celulose em Inocência (MS)
Date
2023-08-22
Name
Portal Celulose
Organisation
Portal Celulose
Comment on data source
The news reports that the company held a public hearing to present data about the installation of the project in the municipality of Inocência to the public.

9. Data source #m8d7vJ2E

Type
Government sources
Publication title
Propriedades da Arauco nos municípios de Inocência e Água Clara/MS
Date
2024-08-01
Name
Sistema Nacional de Cadastro Rural (SNCR)
Organisation
Instituto Nacional de Colonização e Reforma Agrária (INCRA)
Email
coordenacao.cadastro-rural@incra.gov.br
Comment on data source
The National Rural Cadastre System, under the responsibility of the National Institute of Colonization and Agrarian Reform, is an official and constantly updated database. However, the database has limitations, namely: 1) it only considers properties bought by the company; 2) the data is self-declared by the owners, meaning there might be more properties. The database is updated monthly (on the 1st of each month).