Deal #10477
Romania
Created at
2024-07-29
Last update
2024-07-30
Last full update
2024-07-30
Land area
Size under contract (leased or purchased area)
- [current] 1380 ha
Size in operation (production)
- [current] 539.72 ha
Comment on land area
The total area occupied by the wind farm, related with the two phases of the project, is ~539,72 ha, from which ~32,27 ha are affected by wind farm construction (access roads, foundations, platforms of wind turbines, 2 electrical substations).
Intention of investment
Intention of investment
- [current] Wind farm
Nature of the deal
Nature of the deal
Outright purchase
Comment on nature of the deal
The area on which the project is located is the property of SC Ialomita Power SRL (After the consolidation, the company is now SC EDP Renewables Romania SRL).
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2013] Startup phase (no production)
- [2015-02, current] In operation (production)
Comment on implementation status
On 11.08.2014 the Environmental Authorization for Facaeni WF - Phase I was obtained. The first phase becoming fully operational in February 2015 when the company obtained the producer licence after the testing period. According to media reports, a second phase of the wind farm or its extension is planned.