Deal #10454

Thailand
Created at
2024-07-17
Last update
2025-01-21

Land area

Size in operation (production)
  • [2025, current] 310 ha
Comment on land area
Size in operation is based on RS polygon generated

Intention of investment

Intention of investment
  • [2021, current] Wind farm (310 ha)

Carbon offset project

Carbon offset project
No

Nature of the deal

Nature of the deal
Lease
Comment on nature of the deal
Leasing agreement is documented in 56-1 One Report shared that the terms were 27 years (Oct 26, 2019 to Oct 25, 2046)

Negotiation status

Negotiation status
  • [2019-10-26, current] Concluded (Contract signed)
Comment on negotiation status
Date is when the lease was signed

Implementation status

Implementation status
  • [2020] Startup phase (no production)
  • [2021-08, current] In operation (production)

Contract farming

Contract farming
No