Deal #10420
Thailand
Created at
2024-07-02
Last update
2024-10-03
Last full update
2024-10-03
Land area
Size under contract (leased or purchased area)
- [current] 376.36 ha
Size in operation (production)
- [2015-02-17, current] 420 ha
Comment on land area
Land area : 2,354 Rais (930 acres or 376.36 ha) based on contract reports
Size in operation is based on the RS polygon generated - its a bit larger due to including roads and warehouses surrounding the solar park.
Intention of investment
Intention of investment
- [2014, current] Solar park (376.36 ha)
Carbon offset project
Carbon offset project
Yes
Comment on carbon offset project
UNFCCC is the creditor
Nature of the deal
Comment on nature of the deal
No official information on the nature. It is presumed to be a lease but no confirming information to back up the nature found.
Negotiation status
Negotiation status
- [2014-09-18, current] Concluded (Contract signed)
Comment on negotiation status
Contract was awarded to Energy Absolute on September 18, 2014
Implementation status
Implementation status
- [2017-02-17, current] In operation (production)
Comment on implementation status
The project has achieved the Commercial Operation Date since 17 February 2015
Contract farming
Contract farming
No