Land area
Intended size
110.3 ha
Size in operation (production)
- [2023, current] 75 ha
Comment on land area
The Machang solar plant – which sits on 110.3 hectares of land and is capable of generating electricity at a capacity of approximately 45 MW of direct current (MWdc) – began operations in April 2023
Intention of investment
Intention of investment
- [2023, current] Solar park (75 ha)
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [2018, current] Concluded (Contract signed)
Comment on negotiation status
In 2018, Idiwan Solar was awarded a contract by the Energy Commission under the second large scale solar programme to develop a 30MWac solar project on land owned by Machang Estate Sdn Bhd and Machang Estate (II) Sdn Bhd.
Implementation status
Implementation status
- [2023-01, current] In operation (production)
Comment on implementation status
The solar plant achieved its initial operation date in January 2023.