Deal #10360

Kazakhstan
Created at
2024-05-31
Last update
2024-05-31
Last full update
2024-05-31

Land area

Size under contract (leased or purchased area)
  • [current] 576 ha
Size in operation (production)
  • [current] 450 ha
Comment on land area
The size under contract is approximate, because it was determined independently in accordance with the cadastre (Data Source 9).

Intention of investment

Intention of investment
  • [current] Wind farm

Nature of the deal

Nature of the deal
Lease
Comment on nature of the deal
According to the cadastral map of Kazakhstan, several plots were found that are registered for the construction and maintenance for this wind farm - cadastral numbers are 02028018140, 02028018141, 02028018142, 02028021159 (Data source 9)

Negotiation status

Negotiation status
  • [2017-06, current] Concluded (Contract signed)
Comment on negotiation status
The project 'Badamsha-I Wind Farm' originates from an agreement, signed in June 2017 by Eni, General Electric (GE) and the Ministry of Energy of the Republic of Kazakhstan, to develop renewable projects in the country.

Implementation status

Implementation status
  • [2018-11-05] Startup phase (no production)
  • [2020-03, current] In operation (production)
Comment on implementation status
The construction works started in December 2018. The first wind turbine generator of Badamsha was successfully energized on 18 December 2019. In March 2020, the first phase of the project was fully put into operation, and the second phase in 2022.