Detailed electricity generation information

Electricity generation
  • [2019, current] Solar (Photovoltaic) 79.5 ha 0 %
    Currently installed capacity: 70 MW Intended capacity: 70 MW

Detailed carbon sequestration/offsetting information

Carbon sequestration/offsetting
  • [2019-07-30, current] Solar park ( 79.5 ha)
    Estimated annual emission reduction/removal: 60000 tCO2e
    Certification standard: No
Comment on carbon sequestration/offsetting
The Mingus solar project was built by a workforce of about 600 local workers and will meet the electricity demands of approximately 28,000 households, while reducing around 60,000 tonnes of greenhouse gas emissions, and saving up to 380,000-litres of water per year.

Use of produce

Has domestic use
Yes
Domestic use
100 %
Has export
Yes
Comment on use of produce
Provide household electricity: 28,000 households