Deal #10224
China
Created at
2024-02-14
Last update
2024-07-22
Detailed electricity generation information
Electricity generation
- [2019, current] Solar (Photovoltaic) 79.5 ha 0 %
Currently installed capacity: 70 MW Intended capacity: 70 MW
Detailed carbon sequestration/offsetting information
Carbon sequestration/offsetting
- [2019-07-30, current] Solar park ( 79.5 ha) Estimated annual emission reduction/removal: 60000 tCO2eCertification standard: No
Comment on carbon sequestration/offsetting
The Mingus solar project was built by a workforce of about 600 local workers and will meet the electricity demands of approximately 28,000 households, while reducing around 60,000 tonnes of greenhouse gas emissions, and saving up to 380,000-litres of water per year.
Use of produce
Has domestic use
Yes
Domestic use
100 %
Has export
Yes
Comment on use of produce
Provide household electricity: 28,000 households