Deal #10221

China
Created at
2024-02-14
Last update
2024-07-17

Land area

Intended size
300 ha
Size in operation (production)
  • [2023-04, current] 226 ha
Comment on land area
Project is built on reclaimed land

Intention of investment

Intention of investment
  • [2022, current] Solar park (300 ha)

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2020-10] Startup phase (no production)
  • [2023-08, current] In operation (production)
Comment on implementation status
Project was inaugurated on Earth Day, as its the largest solar farm in Taiwan