Deal #10193

Senegal
Created at
2023-12-30
Last update
2024-11-07

Land area

Size under contract (leased or purchased area)
  • [2015, current] 49.5 ha
Size in operation (production)
  • [2019, current] 49.5 ha

Intention of investment

Intention of investment
  • [2008, current] Wind farm (49.5 ha)

Carbon offset project

Carbon offset project
Yes

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [2008] Intended (Under negotiation)
  • [2015, current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2018] Startup phase (no production)
  • [2019, current] In operation (production)