Land area

Intended size
150 ha
Size under contract (leased or purchased area)
  • [current] 150 ha
Size in operation (production)
  • [current] 150 ha
Comment on land area
The two solar power projects together are built on 150ha of land

Intention of investment

Intention of investment
  • [current] Solar park (150 ha)
Comment on intention of investment
Solar farm

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2013-01] Startup phase (no production)
  • [2014-05, current] In operation (production)
Comment on implementation status
The construction of the project started in January 2013 and full commercial operations began in May 2014.