Please note: you are viewing an old version of this deal. The current version can be found here: Deal #9733

Deal #9733 Version #88755

South Africa
Created at
2022-12-06
Last update
2022-12-06
Last full update
2024-02-28

Land area

Size under contract (leased or purchased area)
  • [current] 125 ha
Comment on land area
The 125 hectare, 86MW

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
Sonnedix develops, builds, and operates renewable energy projects for the long-term, with a focus on providing green, affordable electricity to our customers

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2016-07-22, current] In operation (production)
Comment on implementation status
In the Northern Cape it officially started commercial operation on Friday 22 July, 2016. Construction was completed after only 17 months. “The project was completed in due time as per the schedule and is now fully operational