Deal #9542

Uzbekistan
Created at
2022-07-18
Last update
2024-09-13
Last full update
2024-05-20

Land area

Intended size
150 ha

Intention of investment

Intention of investment
  • [2022, current] Wind farm
Comment on intention of investment
The Project is proposed to include 111 wind turbines as well as a substation, compound area, tracks to access each turbine, underground cabling from the turbines to the substation and two short overhead transmission lines, connecting to two existing transmission lines that cross the Project site.

Negotiation status

Negotiation status
  • [2021-06] Intended (Memorandum of understanding)
  • [2022, current] Concluded (Contract signed)
Comment on negotiation status
Approval of the Project PZVOS (the National environmental impact assessment mechanism) was obtained in July 2021.

Implementation status

Implementation status
  • [2022] Project not started
  • [2023, current] In operation (production)