Please note: you are viewing an old version of this deal. The current version can be found here: Deal #8767

Deal #8767 Version #94406

Egypt, Arab Rep.
Created at
2021-06-08
Last update
2024-10-02
Last full update
2024-10-03

Names of communities / indigenous peoples affected

Name of community
Ras Ghareb
Comment on communities / indigenous peoples affected
Two smaller communities, Ras Shoqeir and Wadi Dara, are situated further south, approximately 60 km and 72 km away, respectively. The project area falls under the informal authority of the Tababna Bedouin tribe, but no Bedouin reside near the project site

Recognition status of community land tenure

Recognition status of community land tenure
Community traditional or customary rights recognized by government

Consultation of local community

Community consultation
Free, Prior and Informed Consent (FPIC)
Comment on consultation of local community
SESA has been prepared by RCREEE and presented for the public and potentially affected community in 2017.

Promised or received compensation

Promised compensation (e.g. for damages or resettlements)
All stakeholders promised the importance of providing sufficient job opportunities to Ras Ghareb communities and that the area has employment potential.

Promised benefits for local communities

Promised benefits for local communities
Other
Comment on promised benefits for local communities
The project has committed to providing professional training to local communities. It is classified as Environmental Category A by the IFC, indicating that it may have significant environmental and social impacts.