Deal #8229
South Africa
Created at
2020-08-07
Last update
2024-09-11
Last full update
2024-09-11
Land area
Intended size
350 ha
Size under contract (leased or purchased area)
- [2012, current] 350 ha
Size in operation (production)
- [current] 350 ha
Comment on land area
Seems to be fully operational hence full size under contract allocated to size in operation.
Intention of investment
Intention of investment
- [2012, current] Wind farm (350 ha)
Comment on intention of investment
Renewable electricity through the wind power .
Carbon offset project
Carbon offset project
Yes
Negotiation status
Negotiation status
- [2012, current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014-05, current] In operation (production)
Comment on implementation status
The plant began operating in May 2014.Other source indicated that the start date of the project activity – preferred bidder bond lodged 19 December 2011.
Contract farming
Contract farming
No