Deal #7826

Nepal
Created at
2020-03-27
Last update
2023-06-26
Last full update
2023-06-26

Operating Company

Operating company
Actors involved in the negotiation / admission process
  • Government of Nepal Government / state institutions (government, ministries, departments, agencies etc.)
  • World Bank Intermediary
Name of investment project
Kabeli Corridor Transmission Line
Comment on investment chain
The project, with a total cost of 31 million USD, has been constructed with the investment of the Government of Nepal and Nepal Electricity Authority and the soft loan from the World Bank.
Network of parent companies and tertiary investors/lenders
Please click the nodes to get more details.
Legend
  • Is operating company of
  • Is parent company of