Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6602

Deal #6602 Version #76303

Lao PDR
Created at
2015-12-02
Last update
2020-12-09
Last full update
2022-08-17

2. Data source #zLUL0Glp

Type
Media report
Publication title
Vientiane Times
Date
2014-08-14
Comment on data source
"Energy investor Lao Holding State Enterprise (LHSE) has reported that, as at the end of June, construction of the Hongsa Mine-Mouth Power Project in Hongsa district, Xayaboury province, was 87.7 percent complete. [...] “The project has so far cost more than 17.55 trillion kip (US$2.19 billion), which is 79 percent of the total projected cost of over 28.93 trillion kip (US$3.71 billion),” Dr Somboune said. The Hongsa mine-mouth power project will begin energy generation in 2015. It is the largest power plant to be built in Laos, and will have an installed capacity of 1,878 megawatts. Dr Somboune said the 87.7 percent completion included construction of the powerhouse which was 89.1 percent complete, the 500kV and 115kV transmission lines and substation were 99.97 percent complete; and the two dams on Nam Leuak and Nam Kaen for use by the project, plus pipeline systems were 99.9 percent complete. With regard to the coal mining side of the project, the overburden sub pit was 83.6 percent complete; and the overburden main pit and construction of a coal stockyard and infrastructure were 100 percent finished. Dr Somboune said the power plant, which started construction in October 2009 in Hongsa district, is expected to start commercial operations in 2015. The generator units 1 and 2 will begin electricity generation in May and October next year and unit 3 will start in February 2016. The plant will have an installed capacity of 1,878 megawatts (MW) to generate energy of about 12,582GWh annually for the Lao and Thai markets. LHSE was set up by the government in February 2005 to facilitate investment in energy generation, and it holds a 20 percent share in the Hongsa power plant. The Thai Ratchaburi Electricity Generating Holding Public Company owns a 40 percent shareholding in the project, while Banpu Power Ltd of Thailand owns the remaining 40 percent.[...]"

4. Data source #6ksYMhrA

Type
Research Paper / Policy Report
Publication title
The Potential Impacts of Lignite Mining on the Environment and Local Livelihoods in Hongsa District, Sayabouli Province, Lao PDR.
Date
2010-08-01
Comment on data source
The Potential Impacts of Lignite Mining on the Environment and Local Livelihoods in Hongsa District, Sayabouli Province, Lao PDR.

7. Data source #FyMK1Oji

Type
Media report
Publication title
Hongsa Power to celebrate commercial power generation
Date
2015-11-30
Comment on data source
VIentiane Times report on 30/11/2015: "Hongsa Power to celebrate commercial power generation: Hongsa Power Company Limited will hold a celebration to mark commercial power generation at the Hongsa power plant, with two generators now fully operational and the third set to operate early next year. The ceremony will be held at the Hongsa Mine Mouth Power Plant, Hongsa district, Xayaboury province on December 9, and will be attended by high ranking officials of Laos, Thailand and other foreign guests. The first power generator was officially put into operation in June of this year and the second generator began operating early this month, while the third one is expected to begin generating in March next year, according to the company. The plant will help to create revenue for the government for development and to promote the bilateral economic relationship between Thailand and the Laos. The constructions started in 2011 and are expected to finish next year with a 25 year land concession of 76.2 square kilometres from 2016-2041. The company is expected to spend US$3.7 billion on the construction and the plant will have a total capacity of 1,878 MW or 626MW per generator, using 14.3 million tonnes of lignite per year. Under the agreement, 1,473 MW of electricity will be sold to the Electricity Generating Authority of Thailand (EGAT), and 100MW to Electricite du Laos (EDL). Banpu Power Limited, and Ratchaburi Electricity Generating Holding Public Company Limited both share 40 percent, and Lao Holding State Enterprise shares the remaining 20 percent. The Hongsa Mine Mount Power Project is the biggest thermal power plant in the country. The project respects international environmental standards but some people are still concerned about the pollution it might cause. The company cooperated with the provincial Health Department to ensure and follow up the health of current and coming generations. After the project began construction, it created many jobs for local people, especially young workers. According to a 2014 company report, almost 3,000 Lao people are employed in the plant and this number is expected to rise this year. This has improved living conditions of the local people and reduced the number of people illegally working in Thailand. The company highly values its social responsibility to families affected by the project by promoting agricultural projects, livestock breeding and handicrafts to gain an income. However, many families still suffer as the special projects are located far from their homes. The company also assists the community with educational development and health promotion by constructing schools and dispensaries and handing over equipment within the district, as well as road construction works.