Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6598

Deal #6598 Version #76281

Lao PDR
Created at
2015-10-29
Last update
2020-12-09
Last full update
2022-09-22

Land area

Intended size
5 360 ha
Comment on land area
The project will have a total reservoir area of 5,360 hectares.

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
Xe-Pian Xe-Namnoy hydroelectric scheme, installed capacity: 410 MW, developed by an independent power producer

Nature of the deal

Nature of the deal
Lease
Comment on nature of the deal
PNPC signed a concession agreement for the project with the Lao government in October 2012.

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)
Comment on negotiation status
Project Development Agreement (PDA) signed on 14/11/2008, Concession Agreement (CA) signed on 19/10/2012

Implementation status

Implementation status
  • [2014-01-01, current] Startup phase (no production)
Comment on implementation status
Under construction

Purchase price

Purchase price
8 130 000 000
Comment on purchase price
The entire project has an investment budget of about 8.13 trillion kip (US$1,017 million)