2023-10-19
Land area
Intended size
0 ha
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
Nam Ang hydro power project, installed capacity: 41 MW
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
Pre-concession obtained in March 2011
Negotiation status
Negotiation status
- [2010-09-01] Intended (Memorandum of understanding)
- [2014-01-01, current] Concluded (Contract signed)
Comment on negotiation status
Memorandum of Understanding (MoU) signed in September 2010; Project Development Agreement (PDA) signed on 23. May 2014; The project was successfully divested to an Asian private investor in September 2015.
Implementation status
Implementation status
- [2014-01-01, current] Startup phase (no production)
Comment on implementation status
Under construction