Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6526

Deal #6526 Version #75968

Lao PDR
Created at
2014-12-31
Last update
2021-04-08
Last full update
2022-09-16

Land area

Intended size
0 ha

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
Nam Theun 1 Hydropower, installed capacity: 650 MW. It will be the last plant in the Nam Theun-Nam Kading hydropower cascade.

Nature of the deal

Nature of the deal
Concession

Negotiation status

Negotiation status
  • [2012-03-09] Intended (Under negotiation)
  • [2016-06-14, current] Concluded (Contract signed)
Comment on negotiation status
Memorandum of Understanding (MoU) signed on 09/03/2012 to conduct a feasibility study. Concession Agreement signed on 2016.

Implementation status

Implementation status
  • [2019-06-01, current] Startup phase (no production)
Comment on implementation status
construction is still on-going and got delayed due to the pandemic; scheduled to begin operation in 2022