Deal #5425 Version #72436
Congo, Dem. Rep.
Created at
2017-04-04
Last update
2017-04-04
Last full update
2021-04-08
Land area
Comment on land area
Size is not known.
Intention of investment
Intention of investment
- [current] Mining
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Comment on negotiation status
initial feasibility study was conducted between May 2004 and May 2006
Implementation status
Implementation status
- [current] Startup phase (no production)
Comment on implementation status
The company was ready to start operation in 2007, but did not due to legal disputes and amendments to the mining agreement.
Contract farming
Contract farming
No