Deal #4951 Version #70245
Burkina Faso
Created at
2016-01-27
Last update
2017-01-12
Last full update
2017-01-12
Land area
Intended size
1 170 ha
Size under contract (leased or purchased area)
- [2008, current] 1170.0 ha
Comment on land area
Size of Taparko is not known. Size of Bouroum Permit is approximately 11.7. The Bouroum mine site is a satellite of Taparko.
Intention of investment
Intention of investment
- [current] Mining
Comment on intention of investment
Gold
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [2008, current] Concluded (Contract signed)
Comment on negotiation status
Nordgold acquired control over Taparko mine in August 2008 (previously owned by Incanore Gold Mines and the government).
Implementation status
Implementation status
- [2008, current] In operation (production)
Comment on implementation status
Mining at Taparko commenced in 2005, with the first gold poured in late 2007
Contract farming
Contract farming
No