Please note: you are viewing an old version of this deal. The current version can be found here: Deal #3799

Deal #3799 Version #63747

Myanmar
Created at
2013-06-07
Last update
2017-04-16
Last full update
2022-01-25

Land area

Intended size
202 ha
Size in operation (production)
  • [2011, current] 202.0 ha
Comment on land area
Contract is only MoU but no details on the specific intended size

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
dam for hydropower

Negotiation status

Negotiation status
  • [2010, current] Concluded (Contract signed)
Comment on negotiation status
MoU between the secondary investor and the Burmese government’s Hydropower Implementation Dept (February 2010)

Implementation status

Implementation status
  • [2009, current] Startup phase (no production)