Deal #10446
Kenya
Created at
2024-07-14
Last update
2024-07-31
Land area
Size under contract (leased or purchased area)
- [2007, current] 60705 ha
Size in operation (production)
- [2011, current] 10273 ha
Intention of investment
Intention of investment
- [2011, current] Wind farm (10273 ha)
Carbon offset project
Carbon offset project
Yes
Nature of the deal
Nature of the deal
Lease
Comment on nature of the deal
The legal status of the land lease for the Lake Turkana Wind Power (LTWP) project is uncertain and complex. In 2021, a Kenyan court declared the land titles "irregular and illegal," ordering the regularization of the acquisition process within a year. However, as of May 2023, the company had not complied with this order, and the court rejected a request for an extension, leading to the land starting to revert to local communities. Currently, LTWP is appealing this decision, but the legal process remains unresolved.
Negotiation status
Negotiation status
- [2007-10-09, current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014] Startup phase (no production)
- [2019, current] In operation (production)
Comment on implementation status
Construction of the wind power plant began in 2014, and it began operation in 2019.