Deal #10312
Philippines
Created at
2024-05-08
Last update
2025-01-27
Land area
Intended size
2 025 ha
Size under contract (leased or purchased area)
- [2009-09-14, current] 686 ha
Size in operation (production)
- [2014-11, current] 686 ha
Comment on land area
The area consisting of 2,025 hectares lies within the jurisdiction of the Municipality of Nabas and Municipality of Malay in the Province of Aklan
Intention of investment
Intention of investment
- [2009-09-14, current] Wind farm (686 ha)
- [2024-03-08, current] Tourism
Comment on intention of investment
49.2 MW Wind Farm; in 2024, it was opened as an ecotourism center with a viewing deck and center
Carbon offset project
Carbon offset project
No
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [2009-09-14, current] Concluded (Contract signed)
Comment on negotiation status
Awarded with Wind Energy Service Contract (WESC No. 2009-09-002) on 14 Sept 2009
Implementation status
Implementation status
- [2014-03-31] Startup phase (no production)
- [2015-06] In operation (production)
- [2023-11-21] Startup phase (no production)
- [2024-04-04, current] In operation (production)
Comment on implementation status
Phase 1 was commissioned in June 2015, with construction begining in March 2014
Phase 2 construction was reported starting in 2023, and was commissioned in April 2024. However, construction stop for 3 turbines of Phase 2 due to compliance issues.